Construction Information & Updates

In the Spring of 2017 The Town Board contracted with Boswell Engineering to oversee this $11.6 million dollar construction project. You can find two-week updates regarding the construction by clicking the tabs below.

The general time frame of the project is now 24 months with no planned work to occur during the holiday season. Water main improvements have been completed as of December 2017. The sanitary sewer improvements are presently on-going and are scheduled to be completed on or about July 2018. The storm sewer improvements are scheduled to commence construction on or about July of 2018 and are scheduled to be completed on or about October of 2018. The streetscape improvements are scheduled to commence construction on or about August of 2018 and are scheduled to be completed mid May 2018. The roadway improvements are scheduled to commence construction on or about mid October of 2018 and are scheduled to be completed on or about June 2019.