Town of New Castle Administrator’s Report – 06/26/18

Jill Shapiro
New Castle, Town Administrator

Paving 2018

The First round of paving has been completed. During the past month the following roads have been paved:

  • Cardinal Place
  • Croton Lake Road
  • Little Lakes Road
  • Quaker Bridge Road

In addition, the following roads have been rebuilt and repaved:

  • Quaker Ridge Road
  • West End of Glendale Road (other portions were rebuilt and repaved last year)
  • Dawning Lane

Additional Paving is planned for the last two weeks in August based on Con Ed completion of gas main work and on availability of paving and reclamation crews. We are also planning on repaving the northern section of the South Commuter lot. Next summer we plan on repaving the exit road, Woodburn and the parking spots along Memorial Circle. Future paving will involve the repaving of Allen Place lot and Siegel’s lot (across from Susan Lawrence).

King Street Sidewalk Part II (117 to Grafflin)

We are waiting for Con Ed to complete their gas main replacement work along NYS Route 120. As soon as they are done, our sidewalk replacement project can begin. We hope to complete this project in September.

Parking Permits

The 2018-2019 Parking Season has begun. If you have not yet renewed your commuter parking permits, annual and meter from last year- now is the time!

Housekeeping

Town Hall will be closed will be closed Wednesday July 4 in celebration of Independence Day. Town Hall will be closed to the public on Wednesday, July 25 for Records Retention Day. Please plan accordingly.