Town of New Castle Administrator’s Report – 07/11/17

Town of New Castle Administrator’s Report – 07/11/17

New Castle Administrator’s Report – 7/11/17

Jill Shapiro
Administrator, New Castle

DPW Summer Update

The Department of Public Works has been working on road drainage projects this summer before the paving projects get underway. The various areas of road work and maintenance tasks performed and completed by the Highway Unit are as follows:

  • Drainage Projects: The Highway Unit drainage projects:
    • Meeting House Road (completed)
    • Plymouth & Chatham (completed)
    • Mid Place (completed)
    • Devoe & North Place (completed)
    • Whippoorwill Crossing (completed)
    • Kitchel Road (underway)
  • Vac-All and “Jet-Rodding” of Basins in all of the above locations.

The Department of Public Works continues to perform such tasks that are a pre-requisite to the projects of road paving and reclamation.

Drainage projects at Mid Place, Devoe & North Place, and Whippoorwill Crossing

Summer Hours/Clean Up Day

Summer Hours for Town Hall started last week- and will extend through September 1. Monday through Thursday are regular hours of 8:45 am – 4:30 pm and Friday we close at 3:15 pm.

Clean Up day is scheduled for Wednesday, July 26- Town Hall will be closed to the public for that day for mandatory records retention day.

Town Board Schedule for July and August

The Town Board will have a work session next Tuesday, July 18 and then will meet again on Tuesday, August 8. Our first meeting in September will be Wednesday, September 6, 2017.

 

http://us3.campaign-archive2.com/?e=&u=483af98a858b44ebd0fefba65&id=98b5e984a0