By Pizza Station, they will install rebar for the seating wall footing & then install concrete for the footing. Later in the week they will install rebar & then concrete for the actual sitting wall.
By Citibank, we removed the concrete sidewalk by Citibank & excavated for the footings for our new clock. This week they will install rebar for the seating wall footing & then install concrete for the footing. Later in the week they will install rebar & then concrete for the actual sitting wall.
On South Greeley From Pizza Station to 120, next week they will grade for the sidewalk & then pour the sidewalks.
We have excavated the steps by Bank of America. This week they will pour concrete for the steps by Bank of America.
As far as Whispering Pines, they excavated the steps and installed concrete for reinforcement. This week they will install the footings for the new steps and next week install the steps.
As far as the alley next to the old Hall of Scoop building, next week they will place concrete for the sidewalk.
In front of Starbucks, next week they will form the ramp & sidewalk then pour concrete. They will also place concrete for the brick pavers.
As part of the traffic light installation, they started to install the 5 pedestrian poles at the King/Greeley intersection. The pedestrian pole by Starbucks was installed. This week they will install a pedestrian pole by Sotheby’s & George’s Men Shop. We will be excavating for the pedestrian pole footings, installing rebar & then concrete for the pole footings. We will also be excavating & installing electrical conduits.
By George’s Men’s Shop, they excavated, installed rebar & will now place concrete for the traffic light pole footing.
Next week they will pour concrete for the sidewalk on North Greeley by Sotheby’s.
On upper King to the project limit by the old Methodist Church, next week they will be pouring concrete for the new sidewalks.
As far as the excavation for the new sitting wall in front of Great Stuff, last week we discovered a buried oil tank. Work immediately stopped work at that location. DEC was notified. When removing the oil tank, another oil tank was discovered. Inspections were done. All necessary remediation is being done. Next week they will install rebar for the footings then install concrete for the footing. Then they will install rebar & then concrete for the actual sitting wall.
As far as the alley way on upper King, they demolished the existing steps & graded for concrete & brick pavers.
From North Greeley to Waka, this coming Saturday they will excavate the sidewalk from the intersection to Waka. Next week they will install electrical conduits & light pole footings then grade for new sidewalks.
Full depth reclamation started last week from 8pm to 6am along South Greeley Avenue. Work began south of the Shell gas station and proceeded north up South Greeley Avenue. This week, at night, they will work to Woodburn to King. During the day they will be working in the parking lane on South Greeley. We will post signs reminding people that stores are open and parking is available behind the stores. Next week they will work on the King & South Greeley intersection.