Chappaqua Downtown Revitalization – June 30, 2019

On Woodburn Avenue (by Pizza Station), this week & next week they will be fabricating the trench drain.  Next week they will excavate for the seating wall, install rebar & then pour concrete.
As far as South Greeley (by Pizza Station), next week they will excavate sidewalk & grade for the trench drains.  They will also excavate for the clock footing & planter/seating wall by CitiBank then install rebar & then pour concrete.
As far as South Greeley (Chappaqua Hardware side), they will continue to install brick pavers.  As far as the alley way (by Chappaqua Framing), they will excavate & install trench drain,  They will place concrete for pavers & start installing brick pavers.
As far as lower King, we are currently scheduled to do the road reclamation on lower King starting on 7/8 and finishing 7/19.  This work will be at night but will effect parking.   The bluestone for the end of lower King will be set this week.
As far as upper King from South Greeley to Senter Street (Family Britches side), we received approval from NYSDOT for the temporary location of the stop sign. Con Ed is “supposed” to relocate a pole.  They will excavate & grade for the curb & work on drainage.  Next week they will excavate for the new seating wall.  They will install rebar, electrical conduits & then pour concrete.