Chappaqua Downtown Revitalization – May 12, 2019

Over the last several weeks, we’ve installed brick pavers on South Greeley from Town Hall to the traffic triangle, and from the library to Bell School. We also installed brick pavers on North Greeley by Rite Aid & across from Susan Lawrence. Next week we will start installing bollards. We will be starting night work next week on Monday, 5/13, to excavate the sidewalk in front of Susan Lawrence & lower King. They will also excavate for pavers in the alley way on lower King. They will work four 10 hour shifts from 8pm to 6am (Mon to Thurs). However, since the concrete plants are only open during the day, granite curb, light pole footings with conduits and sidewalks will be day work. As many have noticed, we have taken down several trees over the last few weeks. Those trees created many root-sidewalk conflicts that damaged our sidewalks. New trees will be planted in the fall. We will be utilizing structured soil to avoid root sidewalk conflicts. Structured soil forces the roots to grow down. You can read about the planting of new trees here   To da