• Pavers on S Greeley by
10/4• Trees going in the week of
10/4 • Final pave the week of
10/11 • Final Project (punch list items) completion by
11/22
On Woodburn Avenue by Pizza Station, they capped the sitting wall. They poured sidewalks. Next week they will install brick pavers. On South Greeley by Pizza Station & Citibank, they finished the clock sitting wall. They poured sidewalks. Next week they will install the clock and brick pavers.
On South Greeley by Bank of America, they poured sidewalks. On South Greeley in the alley next to the old Hall of Scoops, they poured the concrete for the brick pavers. They will install brick pavers the week of
10/07.
On North Greeley by Sotheby's, they poured sidewalks. They will install brick pavers the week of
10/07.
On South Greeley by Starbucks, they poured the sidewalks. Next week they will install the brick pavers.
On South Greeley from the alley (next to Chappaqua Framing) to King, they graded for sidewalks. They started to pour the sidewalks. Next week they will relocate the Belgium blocks and start installing the brick pavers.
On upper King from Ibiza to the sitting wall, they installed trench drains & installed a water line (for the new plantings). They poured the sitting wall & placed the stone veneer. They graded for sidewalks and will start to pour the sidewalks this week into early next week. It’s a 4 day pour. They will install brick pavers the week of
10/07.

By the alley next to Ibiza, they graded for the concrete sidewalk & steps. They poured the steps. Later this week & into next week they will pour the sidewalk.
By upper King from North Greeley to Waka, they poured the sidewalks. They installed pedestrian poles and traffic pole.
By upper King from Waka to Bagel Emporium, they installed trench drains & graded for sidewalk. They poured sidewalks. They will install brick pavers the week of
10/07. This week and going into next week they will also start excavate the tree pits, install tree grates and install top soil. They will start to install the trees the week of
10/07. We have 55 out of 62 trees ready to go.
We have 27 planters on hand. Our street furniture (benches, tables & umbrellas) has shipped and we expect it to arrive soon.