Chappaqua Downtown Revitalization – April 09, 2019

We are currently working from Town Hall to the Shell Station (on the town hall side). We have installed new curbing, footings & electrical conduits for the new decorative light poles & sidewalks. They are now grading & preparing for the pouring of the new sidewalk. Installation of our new decorative light poles has started – from the library to Bell School. We will be installing a total of 57 decorative light poles. We have also installed the foundations for the pedestrian beacons (for pedestrian crossing) along South Greeley. The bricks for the accent strips along the granite curbs have arrived, and will be installed in the near future. The trenches have been excavated for the sitting wall by Pizza Station. We are also currently working from the Post Office to Susan Lawrence (on the Susan Lawrence side of street). Please remember to check the Town of New Castle website for all updates. https://mynewcastle.org/downtown-streetscape-committee/