Chappaqua Downtown Revitalization – May 26, 2019

As far as North Greeley, granite curbing was installed by Susan Lawrence.  Decorative light fixtures were installed.  The sidewalks by Susan Lawrence are graded, and ready for sidewalks.  The sidewalks will be poured on Tuesday & Wednesday.  They will place the concrete for the pavers on Thursday & Friday.  They will installing brick pavers the following week on Wed, Thurs & Fri.

As far as lower King, granite curbing was installed.  Decorative light fixtures were installed.  They started grading the sidewalk.  Next week, they will continue to grade the sidewalk & start pouring the sidewalks on Tuesday.   They also excavated the alley on lower King,  It was graded and concrete was poured.

As far as Allen Place, they excavated the existing curb & sidewalk.  Next week they will form & place the concrete curb, grade for the sidewalk & the following week install the sidewalk.

As far as South Greeley, next week they will be working at night excavating the existing curb & sidewalk from the triangle to lower King (Starbucks side).  During the day they will be grading for the granite curb and installing conduits & light pole footings.  The following week, they working at night, they will excavating the existing curb & sidewalk on South Greeley from Woodburn to upper King.  During the day they will be grading for the granite curb and installing conduits & light pole footings.